DEMOLITION OF THE FORMER CEMENT WORKS - Update October 2018

Residents will be aware that the demolition has now started. The period of works is anticipated for 42 – 44 weeks.  The full Demolition approval document is available below.  All other documentation is on the South Cambs District Council website quoting S/1394/18/FL on the planning page.

The condition residents will be most interested in is the following:

  • No site working including the use of power operated machinery shall take place before 8am on weekdays and 8 m on Saturdays nor after 6pm on weekdays and 1pm on Saturdays (nor at any time on Sundays or Bank Holidays), unless otherwise previously agreed in writing by the Local Planning Authority in accordance with any agreed noise restrictions.   (Reason - To minimise noise disturbance to adjoining residents in accordance with Policy NE/15 of the adopted Local Development Framework 2007.)

Environmental Health at South Cambs District Council are the monitoring authority so any complaints should ideally be addressed to them.

Redrow are planning for the chimney to be demolished on the 20th December (maybe the 21st if conditions not suitable). More information on this will be available via the School as there will be a raffle to see who will push the button!